Springhill Drive Overlay

Project Type:
Road
Project Status: 
Under Construction
Location: 
Springhill Drive
Springhill Drive Hwy 20 to Scenic Dr
Albany, OR

The County was awarded funds from the Albany Area Metropolitan Planning Organization to complete a grind and inlay of Springhill Drive from Highway 20W to the Albany City Limits.  The County is contributing additional funds to overlay Springhill Drive from the Albany City Limits to Scenic Drive.

Status Updates

July 15, 2019 - Grinding to start in selected locations (new date due to weather)

July 16, 2019 - Paving will start at the Highway and proceed north (new date due to weather, but paving should still be complete by the end of July)

June 17, 2019 - Pre-construction meeting held with contractor, North Santiam Paving

June 24, 2019 - Work to start on upgrades to accessible ramps at Hickory Street and North Pointe Drive

July 9, 2019 - Grinding to start in selected locations

July 11, 2019 - Paving will start at the Highway and proceed north over a series of 8 days. It is estimated paving will be complete around July 24, 2019 (Weather dependent)